Published 18:15 on 22 Jan 2025
Great News! Our changing room project is starting soon.
Key Dates:
- Monday, 20th January: Setup begins.
- Monday, 27th January: Construction starts (8-10 week programme).
Phases:
- Phase 1: Monday 27th January - Ladies and gents changing rooms, showers, and WCs closed. Accessible facilities open.
- Phase 2: Expected week commencing 24th March Ladies and gents changing rooms, showers, and WCs reopen. Accessible facilities closed for refurbishment.
Temporary Arrangements:
- With limited facilities on site please arrive ready to sail and change at home if possible.
- The two accessible facilities (unisex) will be open. Please remember to return your bags to your car after use.
- Disabled parking bays are temporarily relocated immediately to the left of the main entrance. Kindly leave these for blue badge holders.
Contact:
- The contractor can only take instructions from our project architect, Jason Aldous, so If you have any questions during the project then please direct them to Jerry, Jenny or Rob.
Thank you for your patience and understanding during this much-needed improvement.